|
Wait another year for elevated road
to Harmandar Sahib
WSN Network
Amritsar:
Visitors to the Sri Harimandir Sahib will have to wait another year
for the elevated approach road as the Amritsar Municipal Corporation
has already taken nearly two years to shift sewerage, water,
electricity and telephone lines to facilitate construction of base
pillars.
By all accounts,
it would take nearly one month to start work on the 0.9-km stretch,
a link to the holy shrine and the Jallianwala memorial from the main
3.25-km segment, where work is already in progress.
The authorities
also admitted that work on the main stretch had been delayed by at
least five months and was expected to be completed by Mayend. Work
on the Rs 173-crore project, including a 3.25-km stretch from
Maqboolpura Chowk to
Bhandari
Bridge and a 0.9-km stretch from the bus stand to Harmandar Sahib,
has been allotted to Gammon India.
An inordinate
delay in completing the project has hit commuters hard, with a main
chunk of the road occupied for construction work and only narrow
service lanes available for plying vehicles.
“Half the day is
wasted in traffic jams on this stretch as I have to commute twice a
day from my house on the Batala road to my office near the
Maqboolpura Chowk,” says Sulakhan Singh, a transporter.
“We are fed up
with the construction work on the elevated road, which has brought
our business on the verge of closure,” says Madan Gopal, who runs a
grocery store.
The project was
started with much fanfare in July 2006, but ran into rough weather a
couple of months later. Launched by the then CM Capt Amarinder
Singh, the project was belatedly brought under the Nehru Urban
Renewal Mission (NURM) with the intervention of Prime Minister Dr
Manmohan Singh and the Centre was to bear Rs 150 crore of the total
cost.
8 April 2009
|